Gross requirements planning is not generating planned orders

Former Member
0 Kudos

Hi

I created finished product with 11 strategy and created two PIR's. Ran MRP but not found the planned orders. Please help

Regards

Anil

Accepted Solutions (0)

Answers (4)

Answers (4)

UmeshMali4994
Active Contributor
0 Kudos

Hello Anil,

Prerequisite for the gross requirement

1.  Strategy group 11 in MRP view 3

2. set the Mixed MRP indicator to 2 on the MRP view 3

After creation of the PIR check in MD04, Requirement created with BSF  “Gross planned indep Requirement”  or not,

Req type is not BSF, then check your PlR user parameter and make sure req type filed  is blank or BSF. (Possible put req type filed blank and save). Rerun the MRP and check,

I hope this information helpful to you ,

Revert back in case of any issue

Regards

Umesh Mali

former_member191663
Participant
0 Kudos

Hi Anil,

Please share the details of the master data.

Also check in transaction MD21 whether planning file entries are created before MRP run. If not create planning file entries and re-run MRP and check.

Regards,

Gururaj Kulkarni

Former Member
0 Kudos

Hi,

Analyse and Confirm your master data first like material master, BOM, Routing etc.

Now mainly in material master set the mixed MRP indicator as 2 and re run MRP with planning mode as 3 then check the MRP results.

Regards,

Narresh

former_member209265
Active Contributor
0 Kudos

Hi Anil,

Have you selected the mixed MRP indicator. This is required for strategy 11.

Better to paste screen shot for MD04 and MRP3 view for the materia.

Hope success.

Regards,

Krishnendu.