on 09-10-2014 6:02 PM
Hi,
I have a scenario where we have ON season and OFF season maintenance. If I create 2 seperate plans for equipment, what is the best way to control the ON season and OFF season plans?
The dormant period will be typically from OCT 15 to June 15. I am not sure how to conttrol this effectively using standard functionalities. Suggestions are appreciated. Thanks.
Hi,
Create a separate Factory Calander by maintaining the special rules in that.If you use this FC, system automatically skips the non maintenance period.
Please find the document in the below link which I have created, this might be useful to you.
http://scn.sap.com/docs/DOC-48570
Best Regards
Kalyan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you looked into using the Cycle Modification Factor, part of the maintenance plan's scheduling parameters?
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Cycle modification factor needs to be updated so that the cycle is updated...which also needs a custom dev fr mass change...
There is a maintenance plan mass change program under aerospace package...I am looking in to the impact of activating it for CPG industry template...
I am wondering how I can use scheduling period to somehow manage the planned dates for seasonal plans..
You can go for 2 factory calendars one for each season.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.