on 09-10-2014 3:16 PM
Hi Experts,
Just a scenario I want to discuss with You all:
Earlier were using non-stock items (no material code,only text to procure materials) and projects were consuming it. Now, we are going to use material codes to procure non-stock items which now have master code for it now the requirement for this process is as below.
considering these requirement i m working on two logic.
Logic 1 .
I configured the material as value based material so that while doing GRN project WBS is debiting
and after consumption of partial material quantity, I am transferring the remaining cost of project to another project by t-code KB61N or KB11N where cost is moving from project to project .
now to show quantity movement i am developing one report which can show the quantity based on moved Price lets say if unit prince is 10 and 200 cost is transferring from project to project means 20 qty is moving in customized report .
Logic 2
With the help of BADI or some development a virtual storage location will be created on MIGO screen
and material will be fetched in this virtual storage location while doing GRN as a referance purpose
and the same location to be used during transferring material from project to project
let me know how far this logic and requirement is correct to code the consumable material and it is going to be codified for reporting purpose .
your earliest response will be appreciable .
Thanks in advance .
Thanks Jurgen
Note is helpful to analyses the requirement .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jurgan ,
scenario is like ,
earlier for these material , material record was not existing
but now business want to create material master for such consumable material for tracking purpose
and these codified material is to procured under WBC and profit and loss account G/L not inventory G/L (balance sheet G/l )
and to pick profit loss G/L i made material as valuate material only so that can populate accounting document while transferring value from project to project via KB61N or KB11N
now what value is transferring from project to project that will be picked in terms of quantity (unit value conversion to quantity ) in customized report
hope scenario is clear now ..let me know if any query you have to give your valuable inputs
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, it did not get clearer to me.
If warehouse want to track movements and store quantity that coming back from projects, then I can just say that creating Non-stock materials was the wrong solution., as you could already know from the name that a non-stock material cannot have any stock. And without stock no movements can be tracked except the goods receipt, but this was already possible without material master.
If you want no inventory value but track quantity and movements, then you have to give the folks a UNBW material.
Hi Jurgen ,
Business wants to track quantity and value both for project based items ( which are to be material coded now )
Considering this , in test server i am procuring these material under account assignment Q w.r.t. to WBS .Now system is picking Inventory G/L but not project G/L
So my query is - Is there any OBYC setting where during GRN system pick project G/l but not inventory G/l
Thanks .
Please read about the design in OSS note: 533207 - Valuated and nonvaluated project stock
look what you wrote:
Now, we are going to use material codes to procure non-stock items
Requirement: Warehouse want to track to moved quantity as well from project to project and to own stock .
Isn't it already contradictory?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.