Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Or Condition in BoM

I want to know how can we create a Bill of Material with Or Condition.

The scenario is we manufacture gases. Now the gas can be made by more than one method so there can be more than one BoM for a gas.

Eg: Same Gas can be made my compressing the liquid or by mixing 2 different types of gas.

I understand that we can create 2 different BoM but than we need to create 2 Prodn Model. How will system find out which model to use in which scenario?

Former Member
Former Member replied

Hi Piyush,

You can create 2 BOM and assign it to 2 different Production Models.

Once you create a production proposal, you can choose different source of supply manually by clicking "change the source of supply" and choose any of the 2 production models which best suits for production.

Hope this will help you...!

Regards.

Samraj

0 View this answer in context

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question