SAP PM Maintenance Strategy

HI All,

     I am trying to create a maintence strategy with scheduling indicator as ACTIVITY and strategy unit as H, and in packeges i have give 8 packages each with an intervel of 250 HRS, in package sequence i got same per hierarchy but from 1250 HRS the sequence is not correct, i must get the same sequence which i got for 250 to 1000 HRS.

Please help me out in sloving this problem. Files are been attached for reference

Former Member
replied

I think I understand what your requirement is, now. You will need to combine the Cycle and Offset settings in your strategy. Specify the same Cycle e.g. 1000, but use the Offset to "shift" the cycles from one another. Please see the screenshot below.