Cost Capturing at the Functional location level not structure?

Former Member
0 Kudos

Hello SAPIENTs,

I have one doubt when I do maintenance on one FLOC say (XX-X-XXXXXX) of complete strsuture this (XX-X-XXXXXX-XXX-XXXX-XX) then the maintenance cost I should get only for this not the segregated cost of structure present below this.

I want to know does system calculate segregated cost till the last level or its gives only the cost at the particular level. I need a choice that I should have entire maintenance cost at (XX-X-XXXXXX). If I want to see entire cost beyond that structure then this option should also be there.

Can anyone throw light on FLOC cost capturing pattern in SAP PM?

Regards,

Kaushal Rai

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Cost capturing will happen only specific Technical Object (Functional Location or Equipment). These will not be inherited to Functional Location structure.

If cost has been booked against the equipment, then these costs will be accumulated on immediate higher Functional location.

There won't be multiple Equipment & Sub-Equipment Cost structure or Functional Location & Sub-Functional Location cost structure.