Hi all,

So I had configured Syclo IM 4.0 using client 200 on our SAP ECC system. Now, I'm trying to change the configuration to use client 300.

I have done the transports between the clients and verified that all the configurations steps are executed. I also changed the JavaBE.ini to use a valid user account and point to client 300.

However, when I try to log in and do the initial synchronization, I'm getting the following error:

Error in initializing the DataTableStepHandler. Please check the ini file or SAP mobile configuration for complex table DTWarehouseConfirmIndicator in sections either DT_MDOID or DT_GLOBAL

Has anyone seen this before?

Any help will be greatly appreciated.

Thanks!