Event Orders in CM25 not re-scheduling in correct sequence

Hi, I have the following issue where I have a block of process orders dispatched which need to be rescheduled to a later date.  I can do this by selecting the group and dragging and dropping, but there are some event type (ZPE1) process orders which are used to capture changoevers in amongst standard process orders, and each time I reschedule the block, the event orders fall out of sequence and are pushed to the end.

Would really appreciate any feedback on this as we are having to manually re-insert the event orders to the correct dates/times every time we reschedule

Tags:
Former Member
Former Member replied

got this resolved by changing the strategy despatch, sequence to SAPSFCAS03 View order - production order

0 View this answer in context