Dear Experts

I'm trying to renew the absence quota for the upcoming year, however I keep recieving a short dump when I am trying to do a batch input straight in production client. Why is this the case, please guide.

Accepted Solutions (1)

Accepted Solutions (1)

GirieshM
Active Contributor
0 Kudos

Hi Sugu,

Can you please share the dump ?

With Regards,

Giriesh M

Former Member
0 Kudos

The dump is no longer showing, I have been waiting for the last hour. Nothing there brother.

Former Member
0 Kudos
GirieshM
Active Contributor
0 Kudos

Hi Sugunthan,

The dump which you received is "TIME OUT" error. You have to run the report in Background mode or Increase the time with the help of basis guy. Prefer to run it in Background instead of changing the parameter to extend the time. And also check any customization is done in the program and Have you done any upgrade recently ?

With Regards,

Giriesh M

Former Member
0 Kudos

Cheers mate, background job fixed the issue.