on 09-09-2014 10:12 AM
Sirs
My client wants to activate ML/Actual costing.
Basic configuration steps I know and help is also available on the forum. Here my question is that:
What kind of working discipline needs to be maintained to use these functionality so as to get good results? Also please guide what are the pros and cons of using ML/Actual costing?
Best regards
Shalabh Shastri
Please go through the below link, & let me know if any more quires apart of from this.
http://scn.sap.com/message/15326883#15326883
The following Decipline need to follow when ML is Active | |
I | ML is to arrive Actual Costing for SFG/FG Material which is activated for ML (S-3) |
II | 1st decipline has to be followed @Material Master Level which will address to All ML Activites |
III | Every Goods movment will effect to the respective month end to Calculate Actual Cost |
1.All Goods Receipts & Invoice Receipts should puch for respective month | |
2.All Production Confirmation & Completion of Order to be happed | |
3.All Delivery & Billing to the respective month should happen | |
4.All Sales return has to be moved from returnSTOCK to Unresticted | |
5.All FI-Cost has to book to respective Cost Centers | |
IV | Actualization of Cost (Prices diffrence) will settled to respective product @month end based upon the sales(charge off) has happened |
V | Once atcual posting ML activities has happened *No Goods movment will happen "Provided ML will get reversed" |
Regd,
Khan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Mansoor
I would be obliged if you please share the pros and cons of activating ML/Actual Costing.
I have gone through the discipline points but want to know 'in respective month' means what? Transaction should happen in the same month or it can happen after the last date (may be a back dated transaction) but before closing of ML?
Waiting for you response.
Best Regards
Shalabh
Hi Shalabh,
Transaction in the same month means, normally business will set off the date for ML closing activities...
Let say, we are in Sep 5... (All stock movement related (GR/IR/Delivery/Sales Return/Goods movement Plant to Plant-STO would effect to to "August- month" it has to to be valuate the Auagust Stock ...need to post on or before 31.August........
Once we do ML Closing we could not post in August....
Hope you clear.....
Regd,
Khan.
Please find the pros and cons
Actual Costing using Material Ledger
Inclusions:
Exclusions:
xCurrent value of procurement costs is not reflected in price
xRaw material consumption will happen at periodic unit price ( previous months average)
xNo real time price will flow during consumption.
xVariances are not reflected in production order
xRevaluation will only happen at the period end
xBench marking is not possible for decision making
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.