Easy Cost Planning - Transfer to Project Budget IMCCP3 ( cj20n vs cj30 )

Former Member
0 Kudos

We are using Easy Cost Planning for Planning Values .

and Copying this to budget CJ30  with IMCCP3 .

For some time no when we are copying budget for some projects value don't match. The budget increases in most cases. and in rare cases budget becomes less than Planned Values

Running CJEN wont resolve the issue , tried many times.

Guys can you suggest .

Raised to SAP they wont reply.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member210673
Participant
0 Kudos

hi ksv,

While using ECP, use Version '0' to record your ECP values and then goto CJ30 to Copy the values from Version 0 (the regular way you do to Copy Plan values).

In CJ30: Edit ->Copy view -> Planned Total

Hope this helps.

-thanks

former_member195427
Active Contributor
0 Kudos

Hi

Seems the issue is with the project version you are using during IMCCP3. Try to create/change a new version and re run IMCCP3 in testing environment and compare the differences.

not sure if it helps.

Regards

Saurabh

Former Member
0 Kudos

Saurabh i check there is only one project Version .

Values in easy cost planning is different with when comparing with  report

S_ALR_87013533 for planned value

former_member195427
Active Contributor
0 Kudos

Hi

The same version has to be active for current year also to update values for current year in IM.

Is it active?

Regards

Former Member
0 Kudos

CJ20N

S_ALR_87013539

Why is there difference in Values?

former_member195427
Active Contributor
0 Kudos

Hi

Make sure that you are viewing both the reports in same currency?

Former Member
0 Kudos

Both currency match.

We are copying planned values to budget .


And value that is getting copied to budget is same as shown in any planned value report 126798 OMR

but we have accounted for 139950 OMR while planning.

former_member195427
Active Contributor
0 Kudos

Hi

I am sure that some where the value is being overwritten upon transfer of value from plan to budget. Please cross check the transactions and the respecting values being passed upon during each transaction run.

Check from AR itself (its plan values) and its approval till transfer to project. You may have to test the process in testing client and then cross check it with your production.

Regards

Saurabh