Error currency invalid when execute Calculates Charges

Former Member
0 Kudos

Hey experts,

I need help. Please anyone see this error:

When we try execute calculate charges the system showing this message.

Thanks

Best Regards

Renato Okamoto

Accepted Solutions (1)

Accepted Solutions (1)

rohit3611
Contributor
0 Kudos

Hi,

Can you Please check if you have maintained a Currency for you Org Data.

This message is raised when

"Currency profile is invalid/not maintained for orgunit in FA customization".

Then you can see the charge profile to organization.

Best regards,

Rohit

Former Member
0 Kudos

Thanks all for reply.

Former Member - I set charge profile, look:

There are others configuration for I do?

Thanks a lot!

Best regards.

Renato Okamoto

rohit3611
Contributor
0 Kudos

Hi Renato,

Is the issue resolved or not?

Please check the currency in PPOMA for this org also....

Best regards,

Rohit

Answers (2)

Answers (2)

tarunkumar
Active Participant
0 Kudos

Hi Renato,

Company code which is parent in you organization hierarchy in PPOME does not have a currency maintained. Maintain the currency and it should work.

Note: You can only maintain a currency for company code and not of Org.

Thanks & Regards,

Tarun Kumar

rohit3611
Contributor
0 Kudos

Hi Tarun,

I also did some debugging and found the same.

Thanks for more information.

Best regards,

Rohit

Former Member
0 Kudos

Friends,

I tried maintained the currency in PPOME but don't work yet. The error continue.

I maintained the currency in my company, because as you spoke, in org. it's can't.

Error

Thank a lot.

Best regards

rohit3611
Contributor
0 Kudos

Hi renota,

DO you want to debug the issue?

Best regards,

Rohit

Former Member
0 Kudos

Came across similar issue and not exactly sure what I've done. But check the charge profile assignment to organization.