Liquidity forecast In FF7A / FF7B - ''M2'' planning level without taxes

Dear all,

I would like to ask you about subject related in  liquidity forecast report (FF7B).

My client requirement is to see the PO amount into liquidity forecast report including tax calculation (At planning level M2).

This is the SAP help text on Planning Level.:

'' In levels for MM and SD, both the amount and the planning date are more uncertain than the amount and date in FI postings, since the vendor may, for example, deliver only a subset or the delivery may be delayed. In addition, the system always displays MM amounts without taxes in the liquidity forecast (in purchase orders, tax is not displayed if it can be deducted; in purchase requisitions, it is never displayed).

I don't know if it'is hard coded to display planning Level ''M2'' without taxes.

Have you please any Idea if we can display ''M2'' Level including tax calculated in PO.

Thank you in advance for your help.

Kindly.

Skander.

Tags:
Former Member
Former Member replied

Hello,

You can find more information and a possible workaround in note http://service.sap.com/sap/support/notes/9861

Regards

1 View this answer in context