Issue with the planning date in Shippment

Dear all,

Is it possible to bring a default date in the Planning field in the Vt01N. my client want to bring a default date can be delivery date or current system date.

is it possible in std SAP.

Please Help

Regards

Former Member
replied

Hi,

   You may follow the below steps:

   1. Go to 0VTK transaction and go to details of the shipment type.

   2. Maintain the copy routine as 8 or 9 as shown below:

  3, Maintain the shipment deadlines in the delivery header - shipment tab.

4. Add the delivery to the shipment doc in VT01N.

5. Go to shipment overview and click on "planning" button. Now, the system will automatically copy the dates from delivery document.

   Please test the scenario and revert back.

Note: There is another option to default the planning dates using planning profile. Here, you can default the dates based on dynamic variant also. If the above option doesnt suit, I'll explain the planning profile option.

Regards,

AKPT