Dates for Backwards scheduling when MRP Run

Hello experts,

When MRP run, which calendar does SAP take to schedule planned orders? where could I indicate it?

Thanks in advance.

Laura

replied

Laura,

MRP considers Plant factory calender for scheduling and dates determination Please check SCAL for FC.

Check OP03 for FC assignment to your plant.

Br

KK