on 09-08-2014 5:41 AM
hi Gurus,
is it possible to get STO proposal through Scope of Planning.
the scenario is like this i have 2 plants and i configure scope of planning for all the 10 plants.
plant Req quantity exist quan planned recp
A 500 200 150
B 600 300 500
in the above case if i run the scope of planning will system transfer the planned recp of plant B to Plant A because planned recp of plant B is more than its req quantity. is it possible through standard and what is the scope for development.
regard
mahesn.
Mahesh,
Scope of planning by itself will not transfer requirements from one plant to another.
The normal way to transfer requirements from one plant to another via STO is to add a special procurement type to the material master; similar to standard SPT 40. OMD9.
Stock Transfer from Plant to Plant - Special Planning Processes - SAP Library
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.