Hello guys,

I performed remote client copy, SAP_ALL from CRM Prod to new QA client.
Now it is finished, but status says "Post-Processing Required"

Warnings and Errors:

Table Name                                                 Component                      Package

/SAPCND/CC_COND_TABLE_MATCH           AP-PRC-CON                Post-Processing Require

According SAP Note 1873757, I tried to run report RGUGBR00 on SE38, but this report doesn't exist.

Is my new client OK or i should perform some other tasks?
Also how to change the status from Post-Processing Required" to "Successfully Completed"