Planned order reduction in REM scenario

I havent worked on REM scenario before (all my exp is in discrete) so my question might be quite basic...

lets say I have 3 planned orders po1, po2, po3 for a material running on 3 lines.

po1 - 100 quantity

po2 - 150 quantity

po3 - 100 quantity

I have done scheduling using MF50 and schedule is released to the SFC.

now, when I go to MFBF screen and just enter the material number and post backflush + gr (which is the normal case almost all rem clients do, if i am not wrong) for quantity 75, which planned order will be reduced? how does system determine which planned order to be reduced? is there any logic?

Former Member
replied

SCM,

All your understandings are correct and Please test let us know if you have any further questions.

Br

KK

1 View this answer in context

Helpful Answer

by