Fellow Consultants ,

We are creating a PO with respect to Project/WBS .

The Project will have Activities that Vendor is supposed to Complete  for the created PO.

The vendor will give Confirmation on completion of activities  after which Activity will be manually confirmed in SAP .

How can this confirmation Trigger Vendor Invoicing .

Accepted Solutions (0)

Answers (2)

Answers (2)

MTerence
Active Contributor
0 Kudos

Hi KSV,

Are you referring to Service Entry Sheet ?

A PO will be created against a Service (Activity) going to performed by the vendor. This PO will be converted to Service Entry Sheet and the value is paid to customer.

refer below doc for more information

Entering and Accepting Services Performed: Service Entry Sheet - Materials Management (MM) - SAP Lib...

Regards

Terence

Former Member
0 Kudos

Dear Maria,

Aginst Service Entry ML81N the process can be carried out, but our reqt. is based on Network/Activity confirmation the payment has to be done .

MTerence
Active Contributor
0 Kudos

Hi KSA,

Sorry, couldn't understand your business requirement.

If you say activity confirmation is it an internal or external activity.


If its an external activity (PS04), the work confirmation (service) can be done via service entry sheet.

In case you are looking for some other answers, Can you brief your requirement again ?

Thanks

Terence

Former Member
0 Kudos

Hey Maria,

we will create project and for that project we will create 1 single PO with 1 line item stating that cost of the constructing project that has to be paid to the vendor for his services (this services will also include materials , but we will consider it as services ).

So in short 1 PO for 1 project -> this will have 500 services to be performed .

Now we have grouped this services as activity for project . first 10 services (1. labour for digging

2. Machines for digging 3. Materials for digging etc. ) as Digging activity in project.

Next 10 services wil be for concrete filling .

Next 10 services will be for wall erection.

and so on.

Now this activity are to be confirmed in Project system and after we confirm activity , the services in PO has to get invoiced .
We can manually update service entry sheet and simultaneously confirm activity in PS.

But we need some link between Activity and services in PO.

former_member195427
Active Contributor
0 Kudos

Hi,

Please check the following thread and the comments from Mr. Navaneetha on it , may be it will help you:

Regards

Saurabh

Former Member
0 Kudos

Saurabh can you help understand the process .