on 09-06-2014 6:37 PM
Hi,
This is our first Process Observer implementation. I'm using a custom BOR object to track an end to end process.
My Activities begin with the receipt of new or updated data from an external system and ends with a Goods Issue / Receipt Document Create.
I've assigned #1 as the Start and #5 as the End of the process.
I've been testing and the POC_MONITOR is picking up the Starting Tasks great!
However, I have some processes that should have been put in a Completed Status since they've hit their Ending Task. In this case, it was a Goods Issue.
But, if you notice, it's still in "Running" status.
How do I get this process to "Complete"?
Thanks,
Robert.
solved in the Process Observer discussion forum:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.