Release Retrigger in PM Order

Former Member
0 Kudos

Dear All,

If anybody add new line item in component tab of existing document, then release flag should re trigger or not? If not then why? If should happen then how? Please help me.

Regards

Sanjeet

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member193016
Participant
0 Kudos

Hello Sanjeet.

No, no re-release of the WO. Why? By releasing you approve the job, not the parts. On the printed pick list the old parts will have status printed (PRT).

Best regards,

Sorin

P745394
Active Contributor
0 Kudos

Hi , Once release it cannot go to previous status usually companies use user status to indicate the changed or added component information.

Regards,

Srinivas

Former Member
0 Kudos

Thanks for reply..If we can change status manually, then why not we can change automatically?

Regards

Sanjeet

peter_atkin
Active Contributor
0 Kudos

Sanjeet

You cannot reset the REL system-status once it has been set (as described above).

If you want to control addition of labour, materials, etc onto an order after release, then you can either try it via user-statuses, or via development.

PeteA

MTerence
Active Contributor
0 Kudos

Hi Sanjeet,

To keep up the industry standards, we are planning the work order before release. But certain cases due to business requirements, users will be tend to update additional material components, which will be done after release only.

As per SAP design, you can change work order CRTD status to REL, but you cannot revoke the status back to CRTD.

Once released, it is released and you can plan additional labour or material, it only affect the KPI.

Regards

Terence

Former Member
0 Kudos

Dear Maria,


But certain cases due to business requirements, users will be tend to update additional material components, which will be done after release only.


In this case how to handle the budget, and  release as well. We have scenario after release document, system will check custom budget table and material issue slip printout for issuing material, later on added component in PM Order, its not triggering in reservation slip.


Is there any other control provision.


Regards

Sanjeet

S0022314014
Active Contributor
0 Kudos

Hi Sanjeet

Due to the nature of Maintenance Work, a planned and scheduled order after release may need further planning and scheduling. Reversing release is, as Ajit Kumar wrote, is not possible.Reversing would have lots of impact on the already triggered functionality like reservations, requisitions etc.  There are ways to identify the plan steps before release and after release. For example, by checking the change log etc.

Regards

Savas

ajitkumar
Active Contributor
0 Kudos

If you are refering to the release of PM order, it wont get back to unrelease status when a component is added.

Release is also possible based on value using the functionality of permits ( Structure CSEVPERMIT )

if you check, you can find a blog in scn on that.

Pl check whether you can get a workaround using that