Dear Experts,
I have correctly maintain the business requirement in OPU7.
But for special set of orders, I want to change the Scheduling Parameters in Order Header.
Eg: "Do not adjust basic dates, dep.reqmts to order start"
But in my system "Adjust dates" field is not editable in the order header.
how can I activate this field?
I want get the Component requirement date into order start ( Only for this order )
Thanks in Advance
Ashok M
Hello Ashok,
You will be able to change these dates through Operations' Dates. In the Operations tab select all operations and give your new Scheduled start and Scheduled finish times in the Restrictions screen area under Must Start on and Must Finish On fields (See picture below). When you do this for all operations, the Scheduled start and Scheduled finish values in the Dates screen of Order Header will be automatically updated.
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.