Phase wise planned and actual time

Former Member
0 Kudos

Hi,

When we confirm the process order using cor6n (enter time ticket for process order), based on the details maintained in the master recipe and yield entered, various times are proposed which we can overwrite and save the confirmation.

I want to get the details of phase wise planned (Proposed time) / actual time for parameters maintained in SAP key (Machine/Labour/Time etc)

Please let me know from where we can get the details planned time and actual time.

Regards,

Smart

Accepted Solutions (1)

Accepted Solutions (1)

former_member184737
Active Contributor
0 Kudos

Hi smart bora,

     Have you tried with COOISPI by using change layout option? You can find many fields which you want in that report. Just click on change layout and add the fields which you want to display.

Thanks

Former Member
0 Kudos

Hi Sankar,

We do not get the planned hours in that.

Regards,

Smart

Answers (3)

Answers (3)

former_member200568
Active Participant
0 Kudos

1) I guess thorough t code COID u can check capacity requirement & Confirmation of Process orders according to given input.

It may not completely suits your requirement but can help you in some way.

Regards,

Deep D

former_member200568
Active Participant
0 Kudos

Hi,

Please check the following tables:

For Planned data

From AFKO

Input: AUFNR ( Process Order )

Output: AUFPL (routing No)

From AFVV

Input : AUFPL

Output: VGW01 to VGW04 ( Std Timing of phases in process order) i.e. m/c time , run time , OH time

For actual data:

From table : AFRU

Input: Process Order ( AUFNR )

Output: ISM01 to ISM04 ( timing of actual confirmation of phases )

further more you can try MCPH , MCP7 standard SAP reports.

kiran_kumar179
Active Contributor
0 Kudos

Smart,

Did you check the order cost analysis from header menu bar?

Check below reports KKBC_HOE and S_ALR_87013162 see if that helps you?

Br

KK

Former Member
0 Kudos

Hi Kiran,

No we do not get phase wise time details.

Regards,

Smart

kiran_kumar179
Active Contributor
0 Kudos

Smart,

I do not think in standard you would get a report which meets your requirement.

Check BADI - WORKORDER_INFOSYSTEM it might be helpful to you.

Br

KK