Severe error(s) occurred in phase MAIN_INIT/UVERS_CHK!

Former Member
0 Kudos

Hello All,

I get this error  during in phase MAIN_INIT/UVERS_CHK!

Last error code set: RFC login to system PJ1 ashost dkrdssap342 nr 01 gwhost dkrdssap342 gwservice sapgw01 failed with code 2 key : Password must be changed.

Any Idea which RFC ai need to check, RFC for PJ1 system on PJ1 has no password?

Thanks for any help.

Accepted Solutions (1)

Accepted Solutions (1)

Reagan
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Reza

Are you able to login to the system with the DDIC user ?

Regards

RB

Former Member
0 Kudos

Hello Reagan,

Thanks for reply,

Yes problem was DDIC password, now I get this error

2 ETQ373 parameter "JOBCOUNT" = "15530100"

2 ETQ373 parameter "IV_VERIFY" = " "

1 ETQ234 Call of function module "SUBST_CHECK_BATCHJOB" by RFC succeeded

4 ETQ010 Date & Time: 20140904155301 

2 ETQ373 parameter "JOBSTATUS" = "A"

2 ETQ374 parameter "RC_CHECK" = "0"

2 ETQ373 parameter "JOBENDDATE" = "20140904"

2 ETQ373 parameter "JOBENDTIME" = "155301"

2EETQ262 Batchjob "RDDIT008" aborted

1EETQ399 Last error code set is:

1EETQ204 Upgrade phase "BATCHCHK" aborted with severe errors ("20140904155301")

I can see on SM37 the Batchjob "RDDIT008" was canceled,

Job started

Step 001 started (program RDDIT008, variant , user ID DDIC

Log cannot be written (existence? authorization?)

Job cancelled

I can see the DDIC user har sap_all and SAP_new rolles.

Any idea about this?

Thanks

Reagan
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Reza

Can you provide the log BATCHCHK.LOG and BATCHCHK.ELG please ?

Check this SAP note if the logs contain errors mentioned in the note

1972214 - Error in Upgrade : batch job fails with this error "Log writer aborted with RC 1"

Regards

RB

former_member182657
Active Contributor
0 Kudos

Hi Reza,

Kindly follow SAP note  46305 - RDDIT008 terminates in phase BATCHCHK

Regards,

Gaurav

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi Reza,

For this error,

Log cannot be written (existence? authorization?)

These are the reason for termination, in general


No write auth to the sub-directories of the upgrade directory (subdirectories bin, log, tmp, ...)

No freespace in the upgrade directory

The upgrade directory cannot be reached from the batch host specified.

Regards,

Divyanshu

Former Member
0 Kudos

Hello,

I had added to file, There is no .LEG file.

Thanks

Reza

Former Member
0 Kudos

Hello Divyanshu,

Thanks for reply,

There is more than 50 GB Space on upgrade directory.

Thanks

Reza

Former Member
0 Kudos

Hi Gaurav,

I had added this  DIR_PUT parameter on default profile befor I start Preprocessing Phase, should I add this on to instance profile too?

Thanks

Reza

Former Member
0 Kudos

Hello All,

I had restart server and tried again error is change to:

ERROR: Batchjob RSVBCHCK failed. Detected the following errors:

# F:\Reeje\SUM\abap\log\RSVBCHCK.PJ1:

       1 ETH010XRSVBCHCK: Check of open update requests

       2EETG050 Update records still exist - Please process

-------------------------------------------

4 EPU201XBEGIN OF SECTION BEING ANALYZED LASTOFFSET                  806 NOW BEGIN OF JOB_RSVBCHCK_PRE =========

1 ETH010XRSVBCHCK: Check of open update requests

2EETG050 Update records still exist - Please process

4 EPU202X====MARK ANALYZED SECTION==== END OF JOB_RSVBCHCK_PRE ======== BEGIN OF JOB_RSVBCHCK_PRE ==========

1 ETH010XRSVBCHCK: Check of open update requests

2EETG050 Update records still exist - Please process

4 EPU202X====MARK ANALYZED SECTION==== END OF JOB_RSVBCHCK_PRE ======== BEGIN OF JOB_RSVBCHCK_PRE ==========

1 ETH010XRSVBCHCK: Check of open update requests

4 EPU202X====MARK ANALYZED SECTION==== END OF JOB_RSVBCHCK_PRE ======== BEGIN OF JOB_RSVBCHCK2 =============

1 ETH010XRSVBCHCK: Check of open update requests

2EETG050 Update records still exist - Please process

4 EPU202XEND OF SECTION BEING ANALYZED END OF JOB_RSVBCHCK2 ================================================

Thanks

Reza

Former Member
0 Kudos

I had find to update records with error on SM13, I think it is the problem.

Reza

former_member182657
Active Contributor
0 Kudos

Hi Reza,

Clear all the error locks under SM13 and retry the phase again.

Regards,

Gaurav

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi Reza,

Have a look at sap note - 67014.

That should solve your issue.

Regards,

Divyanshu

Former Member
0 Kudos

Hello

Yes I did and find another error , now I can continue.

Thanks for help

Reza

Former Member
0 Kudos

Hello,

I am during main_shdpreput/start_shd_preput and the Shadow instand can not start. dispatcher is stopes.

I had added DEVTRACE.log file and developer trace.txt, Is it some body had the same problem on shadow instance.

Thanks for any help.

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi Reza,


*** ERROR => [CreateOsShm] CreateFileMapping(73,58800 KB) failed with Err=1455

              ERROR_COMMITMENT_LIMIT: The paging file is too small for this operation to complete. [shmnt.c      2263]

For the above error you can refer:

PXA_NO_SHARED_MEMORY - ABAP Development - SCN Wiki

Refer:

1518419 - Page file and virtual memory required by the SAP system


Adjust above part and try again by taking a restart.

Regards,

Divyanshu

divyanshu_srivastava3
Active Contributor
0 Kudos

You have uploaded one more dev_disp 

Can you share dev_ms and dev_w0 please.

Regards

Former Member
0 Kudos

Hello,

Thanks for reply.

I had add dev_disp and dew_0 , from SUM,

Thanks Again

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi Reza,

Same error -


I  *** ERROR => [CreateOsShm] CreateFileMapping(43,379755 KB) failed with Err=1455

              ERROR_COMMITMENT_LIMIT: The paging file is too small for this operation to complete. [shmnt.c      2263]

I  *** ERROR => ShmCreate: Create (43,388869136,1) failed [shmnt.c      535]

How much of RAM how you have ?

Can you increase virtual memory and set paging file ?

Refer:

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/300cc754-45a0-3010-79b9-f7a5395a2...

And the note that I have asked you to read.

The same note has one more linked note, have a look..

Regards

Reagan
Product and Topic Expert
Product and Topic Expert
0 Kudos

First try to reduce em/initial_size_MB to a smaller value.

At present it is set to 17199MB. If possible set it to 8 GB and restart SAP.

If that doesn't help then follow this SAP note

1997262 - The shadow instance won't start up. System dev_w* trace files highlight error message 1455...

Regards

RB

Former Member
0 Kudos

Hello Divyanshu,

Thanks for reply I had increse memury, But I cannot restatr server now, This is production server.

I will restart the server leater and come back with result

Thanks

Reza


divyanshu_srivastava3
Active Contributor
0 Kudos

Please check the reply from RB.

A further/correct tuning can be done from note referred by him.

Regards

Former Member
0 Kudos

Hello Reagan.

Thanks again

This is from main instsnce, Is it not ok?

Former Member
0 Kudos

Hello,

I will  refare in to 1997262 note now

Thanks aain

Reza

Former Member
0 Kudos

Hello,

Thanks for all helps, I did used this note and now shadow startet,

Thanks Again

Reza

Answers (1)

Answers (1)

former_member182657
Active Contributor
0 Kudos

Hi Reza,

Nice !! Kindly close the thread.

Regards,

Gaurav