on 09-04-2014 8:10 AM
Hi Experts,
In tcode RERAALCN key date will always be period end date.
In our fiscal calendar we have following end dates:
2/08/2014-Period end date for July
30/08/2014-Period end date for August
4/10/2014-Period end date for september.
Rent is always paid 10 days in advance for every month.
For 2/8/2014- Rent paid for month of August in july is displayed correctly
For 30/8/2014- We want to display rent paid for the month of september in August.But it is displaying results only for august
not for september.
How to resolve this issue.
I have looked into FM 'ACE_DS_METHOD_LINEAR_P1' , but here I am unable to modify code with expected results.
Thanks & Regards,
Greeshma.
Hi All,
Thanks for the input. Issue has been resolved by changing configuration.
Thanks and regards,
Greeshma.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Greeshma,
have you checked the BADi
Thanks & regards,
Bharat.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Greeshma,
Have you considered the option of changing the frequency for the Accrual Engine posting to 'Per Posting Period'. Please refer the below mentioned path.
Flexible Real Estate Management (RE-FX) -> Accounting -> Accrual/Deferral -> Accrual/Deferral -> Accrual/Deferral Posting -> Define Posting Control
If this solution does not fulfill your requirement, you can go ahead with an enhancement.
Regds,
Hardik Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.