How to Assign Model or Version

Former Member
0 Kudos

Hi Experts,

I have created one new model and version, After CIFing my master data from ECC system, how to assign master data directly to my created new version and model.Please explain bit clearly.

Thanks & Regards,

Sreenivas.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member190993
Active Participant
0 Kudos

Hi Sree,

The master data CIFed from ECC is already assigned to active '000' model. As suggested by Sourabh, you now need to copy this master data from active model to your model. You can use t-code /n/sapapo/vercop for copying the same to your model.

Regards,

Umesh

sourabh_jain66
Active Contributor
0 Kudos

Hi Sree,

You should first transfer the data to active model / version and then do the copy, Please check below thread for copying model and version, should help you.

Creating, Copying, and Deleting Models and Planning Versions - Supply Chain Model, Planning Version,...

Rgds

Sourabh