09-03-2014 8:34 AM
Hi
Planing to use budget release process on monthly basis, done relevant configuration but release process is not working
For release done following configuration:
Define Release Scenario
Define Budget Types for Release
Assign Budget Types for Release to Processes
Kindly advice where I am missing
Regards
Upendar
09-03-2014 5:29 PM
09-04-2014 9:27 AM
Hi
In addition to my query..
I am trying to post budget in FMBBC with BCS Value Type = Budget, Process = Enter, Budget category = 9F, Document type = Budget entry, Budget Type = Budget Initial
Once I save this data it is appearing in FMRP_RW_BUDCON consumable budget column, I think release process is not working properly.
Can any one please advice on this functionality.
@Eli Sir
Could you please throw some light
Regards
Upendar
09-04-2014 6:03 PM
select the document of you budget, You must create the document for release with reference
Option "Document" -> Create according Reference "
Then,
Where it says Type Value = R1 Liberation
Document Type = Liberacion
Class = Liberacion Budget
Save and then sap release the budget amounts.
In summaryt you should configure customizing for release, you must create document for release
09-04-2014 7:09 PM
Hi
Many thanks for reply
Created a separate document type for budget entry and release
Requirement is: one time in a year user will 12 month budget, then month on month budget will be released
In my case budget release process is not working, without release it is allowing to consume budget?
Regards
Upendar
09-04-2014 10:40 PM
Each budget document may represent a month. (field period in screen, by default is 0)
then you will have 12 documents budget
You must create documents release (documenntos by reference) and go save (releasing)
Each document released represents one month released
Please check if answers correct
09-05-2014 7:54 AM
Hi,
Unfortunately, your question is not clear. When you say that release does not work, please, be specific. If you see your posted budget in AVC report as consumable budget and you want to see only released budget, then you have to set a filter in AVC for budget types, that only types associated with released budget will be considered as eligible for consumption.
Regarding your comment about 12 months, keep in mind, that AVC works on annual basis; hence, you can speak about 12 portions, but not about 12 calendar months. I.e. releasing budget for January won't mean that you won't be able to consume it in March. If you want to manage monthly budget, you have to work with 'Budget period' FM assignment or with workarounds, which I described on this forum on several occasions.
Regards,
Eli
09-08-2014 8:54 AM
Hi
Thank you for reply
Sorry for later reply
I will explain requirement:
1. we are planning to annual into 12 portions and for this each portion I am trying to use release process
2. Can you please let me know if I want to use release process what is process to be followed, done the following configuration for release process
3. In FMMBC what is the selection we have to use while entering budget with release process
Regards
Upendar