on 09-03-2014 5:25 AM
Hello Friends,
I have this issue. Let me explain this.
Old Landscape DEV ( 210 ) ---> QAS(300) ---> PRD(400)
We performed sysytem refresh, PRD_>QA. But to avoid client copy in QA ( 400>300) and to maintain the Landscape properties, we instead decided
to change the landscape to
DEV(210) ----> QAS(400) ---->PRD(400)
Now, there was one challenge, the Transport request 'x' which was not imported in QA300 - but exported from DEV, had target client "300", we had to import that in "400". We did that by changing the target client in STMS, it was done. The import queue is intact.
But the probem is with STMS_QA, I shall explain.
The transport request "Y" which was already imported in QAS old (300) appeared in PRD and QAS as "To be approved".
This was perfect before sytem copy.
We performed system copy and could get the same "import queue" in QA and PRD.
BUT - I don't get the old QA approval work list.
When I do fresh imports into QAS, QA worklist works fine.
But the old data is gone !
Can I get that back ?
Please help,
hi, i believe you have to export before refresh table TMSQWL and import the same table into the refreshed system.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
if you have request number then you can get it you have do certain things login to dev system
/usr/sap/trans/cofiles request no with KXXXXX.SID
/usr/sap/trans/data request no with RXXXXX.SID
copy this file
QUA
/usr/sap/trans/cofiles request no with KXXXXX.SID
/usr/sap/trans/data request no with RXXXXX.SID
then it will come again into que
STMS_IMPORT
then it will come into qua then you can reimport into qua 400
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
10 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.