Dear All,
I'm configuring and testing the fully interchangeable scenario in MM.
I've created an FFF class and maintained 3 materials (material codes are SE01, SE02 and SE03) as fully interchangeable in trx PIC01.
Then I've created a PO with material SE01. When i push the button "Mat. Replacement" , system creates only one sub-item again with material code SE01. In the item details of the first item, I can see the "Material Replacement" tab. Click on this tab and at the bottom of the screen there is a button called "Other material numbers". When i click that, other material numbers SE02 and SE03 is coming up as second and third sub-items.
What i was expecting is; right after clicking "Mat. Replacement" button, system should show me all the materials in FFF class as sub-items in PO.
I mean why do i have to go into the details and again click another button ? Is this the standart behaviour of the system or am i missing some customizing ?
Best regards,
Found out that this is system's standart behaviour.
Closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.