on 09-01-2014 6:08 AM
Hi all, Is there anyway to set up time based min and max lot sizes? ie we want to have a Max lot size which is small for use with the first 3 months of our plan which starts life in SNP and then converts to PPDS and into blocks for block planning, but months 4 to 36 we want to leave as large max lot sizes as there is no need to have the small max lot sizes for the different horizon.
As far as I can see there is only a material/plant lot size and Max lot size and no way to have a different setting in a different time period.
Thanks
j
Hi John,
As you know, in the product master, the lot size maintenance is time-independent, so that obviously can not be used for your scenario. As per my understanding, to meet this using standard functionality, you can maintain multiple product specific t-lanes (for STRs) and PDSs (planned orders) with required lot size ranges and validity dates (for short or long term horizon). But, again since the validity of t-lanes and PDSs will not be automatically rolling forward so the updating the validities will be a challenge.
The other option could be to enhance the heuristic functionality at lot size selection step while creating order.
Regards,
Umesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.