on 08-29-2014 1:50 PM
Process Orders start/end time are displayed as 00:00:00 in APO but for the same order, time is 24:00:00 in ECC. Where to check/change settings so that both systems display time in same format? Can you suggest tcode or setting to change? Also we think 00:00:00 is preferred over 24:00:00; what do you think?
Dear ,
in the SD schedule lines you can enter dates with the time 24:00:00. This leads however to all kinds of problems in ATP, as 24:00:00 is not a valid time. The last second of the day is 23:59:59, yet SD still allows an entry of 24:00:00. So please use 23:59:59 to avoid further display problems.
Regards,
Tibor