Process Orders start/end time are displayed as 00:00:00 in APO but for the same order, time is 24:00:00 in ECC. Where to check/change settings so that both systems display time in same format? Can you suggest tcode or setting to change? Also we think 00:00:00 is preferred over 24:00:00; what do you think?

Accepted Solutions (1)

Accepted Solutions (1)

tibor_nagy
Contributor
0 Kudos

Dear ,

in the SD schedule lines you can enter dates with the time 24:00:00. This leads however to all kinds of problems in ATP, as 24:00:00 is not a valid time. The last second of the day is 23:59:59, yet SD still allows an entry of 24:00:00. So please use 23:59:59 to avoid further display problems.

Regards,

Tibor

Former Member
0 Kudos

So which transaction/tcode or which setting should be used to make the change?

tibor_nagy
Contributor
0 Kudos

You need just to ensure that 24:00 will be not put manually in sales order schedule line.

Former Member
0 Kudos

Ok.. as of now the problem is with Process orders (/production orders) and time is populated automatically by the system... So I am looking for some setting which could change the format of time in the system...