Hi Experts,
I am getting a message during the CTP check in the sales order creation (VA01) in ECC. Below is the message once I clicks on planning log for CTP check.
What is the "Temporary account assignment" and How can I remove from this planning log to execute CTP perfectly.
I could not see any orders in below mentioned transaction once I saved the sales orders in ECC.
/SAPAPO/ATREE_DSP - ATP Tree Structures
/SAPAPO/RRP_ATP2PPDS - Conversion ATP Tree Structures -> Production Planning
Could some one please help me what I am missing here?
Thanks,
Note the following special features for make-to-order production in CTP:
A separate planning segment is created for every item of a sales order.
The planning segment is linked to the sales order item via the account assignment.
The order number does not exist when creating the sales order. It is not transferred to SAP APO until you have saved the sales order. This means the system has to work with a temporary account assignment when checking new items. The temporary account assignment is not converted into a permanent one until the sales order item is posted in APO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CTP does not create the ATP trees. The ATP trees are used in multilevel ATP. You do not miss anything. It is all correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.