on 08-25-2014 5:50 AM
Hi SD Experts,
Can you please provide the solutions for the below requirements.
Requirement details are below:
How to disable forward scheduling in sales orders....
For My sales order type i already configured in customizing that delivery scheduling should only carry out backward scheduling.
The results is tht no forward scheduling in carried out when material is i stock .. this is ok...
But when there is no stock and ATP indiates an expected inward movemnt, the system ignores the indicator and carries out forward scheduling anyway.
Is there any possibility to change this behaviour?
Appreciate any help....
Regards
Sudheer
Hi
If you do not want the system to switch to forward scheduling automatically, you can specify per plant in Customizing for MRP, in the IMG activity Parameters for determining the basic dates that the system is to continue the backward scheduling calculation even if the resulting start date lies in the past.
Thanks & Regards
Bhaskar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.