on 08-23-2014 2:42 AM
for example, i set the controlling of ATP scope as check with RLT, but the material master data is not maintained with MRP level. when i create sales order, there is no stock, but it can confirm the ATP, can everybody tell me the reason.
thanks a lot.
Hi all ;
When there is no stock available, but you still receive a confirmed schedule line
in the sales order.
Because , the availability check that was carried out included a replenishment lead time in the scope of
check.
Regards.
M.Ozgur Unal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In sales order we will get the confirmed delivery date based on the current stock, inward and outward movement and RLT time.
If you don't have any stock and system won't find any inward and outward movement, also there is no RLT time then it will confirm the today's date only.
So you have to provide any information to get the correct ATP check
Thanks
Suneet
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
RLT can be from:
1. for internal prodution - the total time maintained for RLT in material master
2. for internal production - if (1) is not maintained, the sum of production time and GR processing time, both of which can be maitnained in material master
3. for external procurement - the sum of PO processing time, delivery time and GR processing time, where PO processing time is on plant basis and can be maintained via OMEW
for your case, if material master is not maintained with MRP level, it could be the case that the RLT is 0
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jocelyn
when i create sales order, there is no stock, but it can confirm the ATP,
Answer is also in your question only
if you activated Check RLT In OVZ9 T.code system confirms the stock even stock is not there
And if you have not maintained RLT In MMR System will take goods issuing time /processing time
so No need RLT It is not mandatory
Let me know any doubts
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.