SAP BRIM Provider Order can be submitted but no contract is created (change process ISTD)

Former Member
0 Kudos


Hi Experts,

This question is related to previous entry

Currently provider order (Standard Transaction Type PROV) can be submitted but unfortunately it does not create a provider contract when clicking on "Submit".

No error messages are shown on screen. PPF Actions seems to be ok, as status is green (see attached screenshot)

There are no errors in the order and number range is defined.

Can anyone provide a list of requirements für ISTD process to create a provider contract?

Thank you and best regards

Vanessa

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Findings are that asynchronous contract creation should be disabled in customizing "Define Settings for Transaction Types". Additionally there are relevant corresponding SAP Notes: 1925135 (for SP02) and furthermore 1965276 (SP04) because contract process does need the target process type to create a contract (there is an error in SAP Standard).

Best regards

Vanessa