Hi Experts,
Here i have an issue where CJI5 has 2 line items whereas PR has only 1 line item..
And user deleted the 1 line item in PR and same is showing 0 value in EBAN table too i.e correct.
But when i check in CJI5 report i see the 2 line items and for second line item it shows some value and same is available in COOI table too.
I tried running correction programs RKANBU01, RKACOR04 & RKACOR10 (CJEN & CJBN too), but coudnt fix the issue.
Can anyone of you please throw some light on cause and fixation of this trouble.
Thanks in advance,
Vindhesh
Hello,
First of all i would say you guys are doing a great job..
And i am back with the answer, SAP NOTE 334851 solved my problem.
Thanks,
Vindhesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Vindhesh,
Just one more thing to add here... When you have run correction RKACOR04, please confirm if you have ran it in update mode? IF not, please try doing that once....
You can also refer to SAP note 21649.
21649 - Comparison Totals records <-> Line items in CO
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vindhesh,
This seems to be a bug in commitments, check whether this note is useful... lets see whether this resolves your issue.
100409 - Commitment without purchase order or purchase requisition
Since this is a bug, you can raise to SAP to fix it.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vindhesh,
Can you please share screen shot of 1)PR line item for its valuation tab And 2) CJI5 view for that line item.
Meanwhile, can you please check that no any PO is created for that line item (because sometimes even though PO is created,PR can be deleted if proper MM validation is not in place). Also, in 'Quantities' tab of PR line item,mark it as closed and check again.
Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check few things:
1.Can you please change the layout(select a different layout) and check the report again.
2. Go to S_ALR_87013558 report and check the commitment value for this WBS (navigate it through GoTo->Line Items),check if it commitment is added of this PR in this S_ALR.. report.
Please check and confirm.
Just to ask, what is the cost element type for the G/L used in this PR line item?
Regards
Saurabh
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.