Aggregated planning in SNP not working

AA3
Participant
0 Kudos

we are using the standard hierarchies structures provided in the  system (SNP_LOCPROD) -RELS_LOKATIONSPRODUKT

to create our hierarchy in (hierarchy maintennce)

we also created Dummy Loc and Dummy Prod under which we have 2 level hierarchies , and using standard planning book 9ASNPAGGR and planning area as copy of 9ASNP02

isssue is we are unable to aggregate the demand to the Dummy Product.

please let us know if there are any specific configs.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member190993
Active Participant
0 Kudos

Hi Ashfaq

Please make sure you have assigned the location product hierarchy in the planning area on "aggregated planning" tab.

Regards,

Umesh

satish_waghmare3
Active Contributor
0 Kudos

Hello Ashfaq

Please refer below link for SAP Help and a very informative blog on this topic.

Aggregated Planning - Supply Network Planning Run - SAP Library

Supply Chain Management

I suggest you to please refer existing SCN thread on this topic, it will give you very good insight.

Hope this will help.

Thank you

Satish Waghmare