i am little bit confuse in automatic fixed pegging and dynamic fixed pegging
1) In automatic fixed pegging pegging is stable between receipt and requirement element . But I observed that some production order of other sales order pegs to my sales order when it is automatic fixed pegging . so how can it be stable
2)when I create manual planned orders it comes under dynamic pegging but these are also stable when it pegs to sales order
3)Give me exact difference between on these pegging
thanks in advance
Regards
Virender
Hi Virender,
In dynamic pegging, the system automatically links the receipts with the requirement for a location product. If the receipt or requirements are changed (qty/dates or any new receipt/requirement is created), new dynamic pegging are created in the system. Therefore the dynamic pegging is not retained for long in the system. You can view the pegging relations and qty pegged on the pegging overview tab in product view (PPDS) or in planning book (SNP when using CTM).
On the other hand, in fixed pegging, the link between the receipt and requirement is retained even after the change in the recpt/ reqmnt qty and dates.
You can manually create/delete fixed pegging on the pegging overview tab and also from the planning book.
In using CTM, you have options to use dynamic or fixed pegging on the strategies tab. If working with PPDS heuristics SAP_PP_019 & SAP_PP_011 can be used for creating/deleting fixed pegging relationships.
To test the pegging behavior, review the same on pegging overview, manually fix peg the rect with reqmnt and then you can make changes in the reqmnt/recpt to see the effect on pegging relationship.
Regards,
Umesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear umesh
Generally i create sales order against material if no stock is available heuristics will run and create planned orders .but when i change quantity for same sales order again i go for GATP new planned orders will be created .But when it is automatic fixed pegging planned orders which are pegged should remain why they are lossing when i am running CTP.
If i am wrong please correct it
Hi Virender,
Please reveiw this.
Converting ATP Tree Structures - Check out the prerequiste.
https://help.sap.com/saphelp_scm50/helpdata/en/68/46f93a4240065ae10000000a114084/content.htm
Recreating Procurement proposals.
https://help.sap.com/saphelp_scm50/helpdata/en/4b/7c553b82794753e10000000a11402f/content.htmhttps://help.sap.com/saphelp_scm50/helpdata/en/68/46f93a4240065ae10000000a114084/content.htm
Dear Rorie
I am using CTP which calls PPDS when ever planning is required not CTM.I want to know why pegging losses in automatic fixed pegging.
thanks ®ards
virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you are using CTM, the system creates fixed pegging relationships- during the next CTM run, the system can change the pegging relationships.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.