on 08-20-2014 3:35 PM
Hi. I am looking for a comparison between 6.8 and 6.10 that outlines functionality changes.
Can you point me in the right direction?
Also, considering upgrade to 6.10....we have custom BAPIs for loading ECC/BI/APO data in the connector runs, should I expect significant changes to those or should they fit right in?
Thanks,
Paul Vogel
Paul
regarding your question about any potential changes to your BAPIs when upgrading from 6.8 to 6.10, one metric that changed in 6.10 is schedule attainment. If your models use schedule attainment, before 6.10 what was used by EIS was schedule attainment loss, after 6.10 what is used is schedule attainment itself, so you should change your BAPIs accordingly. If you don't use schedule attainment then this change doesn't affect your BAPIs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here is the link to a presentation that outlines the functions and features added to EIS from version 6.8 to 6.9 and to version 6.10 including service pack 1. https://scn.sap.com/docs/DOC-65670
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We are also looking for a similar answer.
Thanks,
Will
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Paul and Will,
I have a document that outlines the precise upgrade features added from EIS version 6.8 to the latest version, 6.10. I can upload it here onto SCN although that may take a few days. Contact me directly if you need something sooner. https://scn.sap.com/docs/DOC-65670
David Zatz