on 08-20-2014 2:36 PM
Hi Team,
Pls help to understand the scenario below for ATP;
Sales order requested date is -20.08.2014-quantity 1000
Existing stock - 0
Open production order –date in MD04 and actual end date in PO-21.08.2014-quantitiy 1000
Now when am trying to do ATP check it shows as,
Dely/Conf.Date 23.08.2014 / 21.08.2014 Confirmed qty- why there are two different dates in ATP delivery proposal tab. How 23.08.2014 is showing ? which is the date system considers for ATP?
Thanks for the advise,
Regards,
Vijesh
Moderator message:
Discussion locked.
Reason: Basic & no effort on search & trail.
Suggestion to OP: We would advise you review SCN Rules of Engagement:
A good way to search the forum is with Google. Refer following blog link :
The discussions are not a replacement for proper training.
This blog describes how to use the SCN search: http://scn.sap.com/community/about/blog/2012/12/04/how-to-use-scn-search
Therefore, you need to put some effort in search & trail, before you post your query as discussion. In addition that for better respond, explain your effort & understanding on that. Because " Asking Good Questions in the SCN Discussion Spaces will help you get Good Answers.
Message was edited by Moderator: Jyoti Prakash
Dear Vijesh
Please check factory calendar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vijesh.vijayan
vijesh vijayan wrote after the Moderator posted his comment in initial post:
Hi Venu,
Can you pls help me to how to make the changes in factory calendar
Regards,
Vijesh
It seems like you are ignoring Moderator's remarks.
Again," Discussions are not a replacement for proper training."
Thanks & Regards,
JP
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.