When I make a process order by converting a planned order, the BOM components are not getting copied in the order.
However, if I make a process order by COR1 Transaction, all BOM components are copied automatically.
Please can anyone help here?
Many Thanks,
SAPXPT
Hi,
Check if the Production version or BOM structure is assigned in the planned order.
Also, when you convert the planned order into a process order, is the order type determined the same in both cases?
Take a look of these two things and come back.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check if your all BOM components from APO Planned order are available in active integration model or not. You can check it using T-code CFM5.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.