Simulation Version not showing Activities in Planning Board

Former Member
0 Kudos

Hello,

I transferred an Operative Project to a Simulation Version, it was successful without errors. When I open the simulation version in Project planning board with (planing Board Profile to show activities) activities, it just shows the WBS elements of the project. None of the activities are shown.

Any ideas?

Thanks,

Jag

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Which transaction you use for view activity dates and what is your system release?

Former Member
0 Kudos

Thx for responding. I am using CJ2B for Operative and CJV2 for Simulated version. The System is ECC 6.0 with Patch EA-PS on 600 level 6.

The issue is with Simulation Version.

Thanks

former_member195427
Active Contributor
0 Kudos

Hi,

In planning board, go to 'Options' (one icon is there) then to 'Template' and select for 'objects' and 'templates' as for activity etc.

Please check and let me know if it works.

Regards

Saurabh

Former Member
0 Kudos

Thanks for responding. I have already tried that option, also the planning board profile config is correct. When I view the same Project's Operative version in Planning board it shows all the components, not if i view the simulation version though, it shows only WBS elements.

Thanks,