cancel
Showing results for 
Search instead for 
Did you mean: 

How can I enter actual percentage of completion in the WBS elements?

Former Member
0 Kudos

Hi all !


I Can not enter Actual percentage of completion in WBS elements...!

I have followed these steps in Progress analysis:

1.- In the progress tab of WBS elements I have entered Measurement method ESTIMATION for
progress analysis (Plan&Actual).

2.- In the WBS element I have estimated PLAN percentage of completion 100% in period 8

3.- In the progress tab of network activities, I used ESTIMATION method for Plan and WORK for actual
to calculate the percentage of completion.


4.- I have entered final network confirmations

Actual Start date: 08.11.2014
Actual Finish date: 08.15.2014

Remaining work is cero.

5.- I run Project analysis to display measurement methods with transaction CNE1
and Progress analysis with transaction CNSE5

In Progress analysis the Processing % of work in Network activities is 100% but 0% in the WBS
element

Adj.NAgg.Act. POC (Adjusted non-aggregated actual percentage of completion)is 100% in network activities
POC actual, non-agg.(Non-aggregated actual percentage of completion)is 100% in network activities.

Does SAP calculates actual POC?

Should I manually enter Actual percentage of completion in the WBS elements?

I can not enter percent of completion (actual value) for WBS elements. The field is non editable !

Please help !

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi all !

This is the answer:

Once I entered the Actual dates at wbs element level, automatically the Actual POC field became editable and I could enter the percent of POC.

0 Kudos

Hi Rafael,

I am facing the same problem.

I am using Plan method at activity : Time Proportional

                Actual method at activity :  Work completion

At wbs level Plan and actual is Time proportional.

I am not identified how the "Adjusted non-aggregated actual percentage of completion" and

"Non-aggregated actual percentage of completion"  is calculated.

Please help me for the same.

Regards,

Pradeep