material availability check not being executed

Former Member
0 Kudos

First of all: I’m an SD consultant with limited knowledge about PS

At our current client are we facing an issue with the material availability check in project system orders, created through e.g. CJ20N. The client mentions, that the availability check on the components is not being executed and therefore is effecting their operations

I did check SAP OSS and found the following OSS notes:

01774744           Planning quantity of PIR is not getting updated properly

01745038           BAPI_NETWORK_COMP_CHANGE is updating PBED-PLNMG incorrectly

01774657           BAPI_NETWORK_COMP_CHANGE is not updating PBED-PLNMG –III

Those notes were also implemented

Did find transaction CJBN and did some testing, but did get the message

BL 001

Availability check not activated

I did check transaction

OPJJ and everything looks good.

OPJK and everything looks good

At this point I’m totally clueless on how to resolve the issue.

If you would have any suggestions, pointers or remarks: they would be appreciated.

Thanks and regards,

Jan Pel

Accepted Solutions (0)

Answers (3)

Answers (3)

MTerence
Active Contributor
0 Kudos

Hi Pel,

This can be due to NO CHECK was checked in "Define Checking Rule"

Also if possible post the screenshot of the Availability Check rule and Define Checking Rule, which might break this issue.

Thanks

Terence

former_member195427
Active Contributor
0 Kudos

Hi,

Can you please check whether the configuration of material availability check in PS is proper and in place or not. Please check the following sap help link on material's availability check in PS:

Material Availability Check - Material - SAP Library

Regards

Saurabh

Former Member
0 Kudos

Hi Jan,

In opjk , please tickmark the check box against "Check material availability when saving order". Please check if this setting is done during order creation. Please let me know if this helps.

Regards

Varun