on 08-09-2014 12:01 AM
Dear All ,
I need to know to Calculating the capacity consumption for stock transfers according to this SAP note 1020963 , I have wrong consumption of bucket capacity in SNP
I Have transportation lane with Trans duration as 8 Hours and Transportation Resource with Bucket Capacity 'Mass' 10000 Kg
Please Advise
Regards
Rami
Hi Rami,
Have you check the previous SAP Note:
722706
- SNP: Calculation of resource consumption of stock transfers
If the unit of measure of your Resource was defined in KG, then check the wieght of your product since SNP could be using that info.
Check also that you are running /SAPAPO/SNP01 considering Capacity.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.