Once picking is completed (source and destination HU is same) immediately system says "packing completed" , in fact the next step is packing.

Is it a right behavior in EWM?

If i use outbound without storage process, how the packing status in ODO would be set as completed without any HU.

Thanks,

Ganesan

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Ganesan,

I believe that the packing status is just dynamically determined based on the HU data in the delivery. The status does not consider the process oriented storage control. Therefor I think the behaviour is right.