on 08-02-2014 3:12 PM
Hi Experts,
How is the vendor master change in ECC captured and what is the strategy/check that the BBPUPDVD transaction OR vendor update report uses/does in ECC to pick up the updated vendor with qualified fields for transmission?
Qualified fields -> Purchasing block, curr change, comm method change, etc.
For e.g, if a vendor is blocked for a P.Org today and if we either execute BBPUPDVD OR vendor update job, so how does it determine the change in vendor master in ECC?
Thanks!
Regards,
Karthik
Hello Karthik,
just to complete what wrote Konstantin, those change documents are determined in ECC using CHANGEDOCUMENT_READ function modul inside BBP_SCAN_VD function modul which is called by RFC from SRM (report BBP_VENDOR_SYNC).
Regards.
Laurent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Karthik,
AFAIK, it does not. It just takes the data from the backend and overwrites SRM Data.
If you use Report BBP_VENDOR_SYNC - it reads last time stamp from SRM table BBP_VDSYNC_CUST table and gets the information from backend from this timestamp via change documents.
Regards
Konstantin