on 08-01-2014 9:59 PM
Hi Gurus,
I have configured and tested MISL and location consolidation feature.They work well separately.
But the requirement is as below :
First perform MISL check.
If MISL fails,then location consolidation should happen.
Example :
Product | Plant 1000 | Plant 1100 |
PROD1_05 | 19 pcs | 15 pcs |
PROD1_07 | 5 pcs | 15 pcs |
In the above example as MISL will fail,consolidation should happen at 1000 by :
I have tried below settings but none give the desired result.
A and B assigned in one strategy sequence.
If any of you have tried this scenario or have any ideas,please guide.
Hi Mr. Shankar,
Q) Are you getting correct results in avl. check screen and the problem is that the results don't flow back when you do 'Accept All' ?
If not try this :
Ideally this should be like :
1. One rule condition that finds MISL rule. If this fails.
( note mention switch of ATP and continue working with Rules based ATP)
2. Second is a normal condition which does location substitution.
Now you should at least get the expected results in avl. check screen. pls check and update and then lets review the results.
Regards,
Jit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi SAP Consultant,
Thanks for your reply.The problem is I am not getting the right results in avlb.check screen.
Below are the options that I have already tried (in line with your suggestion).
Locations used : Plant 1000 and plant 1100
Stock scenario as in original post
Option 1 :
Rule A : MISL rule linked to condition type X (with setting 'Switch off...')
Rule B : Normal location substitution rule linked to condition type Y
Rule C : Rule with 'Consolidation location' as plant 1000 linked to condition type Z
Result :
(Attaching the screenshots also if above not visible)
The result is as required for line item 20.
(5pcs of PROD1_07 from 1000 and PR for 11pcs of PROD1_07 from plant 1100 to 1000)
It doesn't work as required for line item 10.
(10 pcs of PROD1_05 from plant 1000 and 15 pcs PROD1_05 from plant 1100.No consolidation in plant 1000)
(this is not material specific)
Option 2 :
Rule A : MISL rule linked to condition type X (with setting 'Switch off...')
Rule C : Rule with 'Consolidation location' as plant 1000 linked to condition type Z
Result :
The result is as required for line item 20.
(5pcs of PROD1_07 sourced from 1000 and PR for 11pcs of PROD1_07 from plant 1100 to 1000)
Again,it doesn't work as required for line item 10 but behaves differently than option 1.
(Only PR for 15pcs of PROD1_05 from plant 1100 to 1000)
Am I missing something in the above ? Or needs a different approach ?
- Shankar
Message was edited by: Shankar Sundaramurthy
Hi Mr. Sundaramuthy,
I have the exact same requirement: MISL first, then consolidation.
Consolidation after MISL seem to be the problem, as it is no problem to perform 'normal' RBA after an unsuccessful MISL check.
Did you ever get the combined scenario to work (MISL first, then consolidation)?
In the consolidation check, are you able to correlate the delivery dates?
With the correlation option available for the consolidation rule, I was expecting the items that are consolidated in the same location to have correlated delivery dates, even if they are not in a delivery group.
Regards,
F. Consultant
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.