Hi,
Business maintains planned costs and revenues on WBS element using Easy Cost Planning tool. But for one of the WBS element system is not allowing to update/add planned revenue line items.User is able to update the planned costs for this WBS element.
The Legend in Easy Cost Planning screen is Non-Changeable Cost Estimate.
The status of WBS is REL,ACPT(Order Accepted),NSCH(Not Scheduled - Forecast Dates),RESA(Result Analysis Carried out).
We have checked all the business process and all the revenue planning is allowed.
Please guide us on how to resolve this issue.
This is resolved...Select the WBS and click on CLOSE icon to reset the cost estimate. This allows to plan revenues again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.