Factory calender and Time stream calender - DP and SNP

Dear Experts,

I have question regarding Factory calender and time stream calender

i understand Factory calender is defined in ECC and CIF to apo for planning purpose in PPDS - correct me if i am wrong

and there is option to create Time stream calender and is used in SNP

here i am not so clear how factory calender is used in DP and SNP and how Time stream calender is used in DP and SNP

can some one explain

when and where Factory calender is used and how ?

when and where Time stream calender is used and how ?

Regards

Raj

Former Member replied

Raj,

Factory calendar doesn't do much of anything in APO unless you want it to.

Factory calendars can be assigned to resources.  Resources in general can be used in both PP/DS and also in SNP.

Factory calendars can be assigned to Time stream calendar (but this is not mandatory).  Time streams can be used in both PP/DS and also SNP.  Two common usages of timestreams are to assign Timestreams to locations, or to Transportation lane Means of Transport.  Such objects can thereafter be used in any APO application, such as PP/DS or SNP.

In DP and SNP, it is possible (but not mandatory) to assign a Timestream to a storage bucket profile.  In this way all the data stored in the planning area may be based upon the data contained in the timestream.

Best Regards,

DB49